Princeton Locker Room Renovation Update | June 24th Men’s Locker Room Construction

Beginning on Monday, June 24th, phase one construction will begin in the Men’s Locker Room.

Renovation Schedule

Men’s

Shower area closes, including sauna and steam room

June 24th – Week of July 29th

Lockers, sinks, toilets remain mostly available with limited access during various phases of the construction. Membership will be frequently updated accordingly.

June 24th – Week of July 22nd

Target closure of entire locker room

Week of July 22nd

Planned completion of renovations

Week of July 29th

The following areas will be affected:

  • The Lavatory Area along with the Locker Area will be available.
  • Showers will be available in the Aquatics Center and in the Family Change Rooms for members who need to shower at the center.
  • Access to the Temporary Showers will be through the Family Change entrance into the Aquatics Center.
  • A Privacy Enclosure will be built in the Aquatics Center to accommodate members while the renovations are taking place.
  • Since shower capacity will be limited during the renovations, we ask all members to please plan accordingly.

Thank you for your understanding while renovations are underway. We’re looking forward to providing you with two beautiful new Locker Rooms!

 

GET THE LATEST NEWS & EVENTS

  • This field is for validation purposes and should be left unchanged.

GET THE LATEST NEWS & EVENTS

  • This field is for validation purposes and should be left unchanged.

Copyright © Princeton Fitness & Wellness Center | All Rights Reserved